Stream Diversion in Central, PA

For a bridge restoration project (erosion-related damage) in central Pennsylvania, we created a stream diversion so that concrete could        be poured under the bridge. We ran 200 feet of piping downstream    and discharged it into a dissipator to slow the discharge.

Included in the system were:

  • 12-inch corrugated hoses
  • Two Atlas Copco PAC F1212 sound attenuated pumps
  • Two Atlas Copco PAS F66 sound attenuated pumps

The project was approved by the local board of supervisors in

January 2024. Work began in March 2024 and concluded in May.